Mine expansion. Exploitation project

Client Watchtower
background resource

June 30, 2026

Increase in mineral production of more than 65%

Necessary:

  • Increased exploitation on the surface and in depth.
  • Modification of the treatment plant.
  • Increase in waste dumps.
  • Dam regrowth.

The work to be done is:

  • Exploitation project with its corresponding annexes.
  • Restoration plan in accordance with 975.
  • Environmental impact study
  • Technical project according to the contents of Annex V of Decree 356/2010.

The preparation will be based on the information collected in the NI43-10 as well as documents such as the geotechnical study, the dam's growth project, expansion designs and the available environmental information that will allow establishing the baseline.